The Riverside Parkway Project began in the fall of 2005. The project costs 68 million and is scheduled for completion in November of this year. However, project manager Jim Shanks says it could be finished as early as this summer.

Tuesday crews were on the 25 Road and 6 & 50 intersection installing new traffic lights prompting some people to wonder how soon the bridge may be open.

Shanks says the bridge is 90 percent completed. $6 million of construction is left on the Riverside Parkway project, says Shanks, $2.5 million of that is for asphalt, which will be laid in the summer. However, if the 25 road bridge is finished early it may be opened to motorists before the rest of the project is completed.

Shanks says the project will alleviate traffic in many different areas, including First and Grand, Fourth and Fifth and Pitkin and in front of the Rimrock Walmart. Shanks says projected traffic numbers suggest the 25 Road bridge could see 15,000 cars per day.


You must be logged in to post comments.

Username:
Password (case sensitive):
Remember Me:
KKCO NBC 11 News
2531 Blichmann Avenue
Grand Junction, CO 81505

Station Phone: 970.243.1111
Business Fax: 970.243.1770
Newsroom Fax: 970.245.3793
News Tip & Contest Line: 970.255.8477
Copyright © 2002-2016 - Designed by Gray Digital Media - Powered by Clickability 17204286 - nbc11news.com/a?a=17204286
Gray Television, Inc.